Subsidence – challenges and consequences

person Finn Harald Sandberg and Kristin Øye Gjerde, Norwegian Petroleum Museum
The seabed on Ekofisk – the neighbouring field to Valhall – was found to be subsiding in the mid-1980s. After this was confirmed by surveyor Bloms Oppmåling, Amoco hired the same company to check Valhall, which has a similar carbonate reservoir to Ekofisk’s.
— From the helicopter deck at Valhall PH, there is a good view down towards QP (the old accomodation platform) and DP (the old drilling platform). Here you can also clearly see the large height difference between the old and the new accomodation platform. The helicopter deck for QP reaches right up to the basement deck at PH. Photo: Shadé Barka Martins/Norwegian Petroleum Museum
© Norsk Oljemuseum
Innsynkning – utfordring og konsekvenser
Ekofisk 2/4 H (the hotel) being jacked up. Photo: Husmo Foto/Norwegian Petroleum Museum

While the geology in the Valhall area is similar, it differs from Ekofisk in reservoir thickness. The latter measures about 300 metres deep, while the other reaches only some 60 metres. Seabed subsidence was accordingly not expected to be as extensive on Valhall. But the 1984 survey showed that the clearance between the field’s platforms and the sea surface had been reduced by 30 centimetres.[REMOVE]Fotnote: Rasen, Bjørn (2007): LF6A. Valhall at 25 … and it’s only the beginning , p 93.

New measurements carried out in June and November 1987 confirmed that the seabed on Valhall had subsided even more and possibly at a faster pace. Fortunately, these initial assumptions proved unfounded. A further survey in 1988 allowed the estimated annual rate of subsidence to be reduced to about 25 centimetres.

Such phenomena in areas with carbonate rocks are not unknown. Chalk has an unfortunate tendency to dissolve when water or other liquid flows through it. The result is the creation of large caverns which can collapse to form sinkholes.[REMOVE]Fotnote: Wikipedia , November 2015. Subsidence is also known from Lake Maracaibo in Venezuela and from US petroleum fields.

Since the problem was not happening so fast on Valhall as on Ekofisk, its installations were in no immediate danger. It might take 10-15 years before anything had to be done – and Valhall’s producing life at the time was not expected to extend beyond 2005.

Further measurements on the field in 1993 showed that subsidence had declined to between six and 10 centimetres per year. The seabed was 2.25 metres lower than when production began.

By the time the licence expired in 2011, the total figure would be just over four metres. Enough freeboard would remain beneath the platform cellar decks to stay in operation.[REMOVE]Fotnote: NTB, 10 March 1993, “Valhall synker, men ombygging kan unngås”.

Injecting water into the reservoir was one way to counteract the subsidence, but Valhall’s chalk structure meant it was seen as less suitable for this method of maintaining formation pressure. Gas injection offered an alternative, but was not investigated in any serious way.[REMOVE]Fotnote: NTB, 29 November 1986, “Valhall synker i samme tempo som Ekofisk”.

Utbygginger på Valhall år for år, feltet, forsidebilde,
Valhall residential platform (QP) on the far left, behind the drilling platform (DP). The crane vessel has been brought in to work on the new process and compression platform (PCP). The steel jacket is already in place. Photo: Amoco Norway Oil Company/Norwegian Petroleum Museum

When Valhall became operational in 1982, the Amoco/Noco group expected it to produce for roughly 20 years and to yield about 250 million barrels of oil. These estimates were sharply upgraded in the early 2000s, when BP had become operator – after merging with Amoco in 1999 – and wanted to continue developing the field. That involved adopting new technological solutions to extend Valhall’s producing life. Some of these related to the reservoir compaction which was causing the seabed subsidence.

The new development plans were based on the government’s approval of a water injection project for Valhall in 2000, and its extension of the field’s licence from 2011 to 20128. An extended production life also meant it would be necessary to do something about the field centre – not least because of the subsidence. Both jacking-up the original platforms – as had already been done on Ekofisk – and the construction of new installations were considered.

Subsidence of the seabed meant that BP also had to build a new process and hotel (PH) platform for the field as part of its further development (Valhall VRD) programme. The choice in 2004 lay between two concepts – two new platforms or a combined structure – and the licensees finally opted for the last of these. That was because they reached agreement on taking power from shore for the new unit rather than installing gas turbines, reducing topside weight. In addition, electrically driven rotating machinery such as compressors required much less maintenance than turbines, were easier to regulate, reducing staffing and speeded pay-back (see separate article on new process and hotel platform).

At the time, the BP group as a whole had adopted ambitious goals for reducing releases of environmentally harmfully gases and chemicals. The company also wanted to use Valhall as a demonstration of the way old fields could be operated efficiently and with a high recovery factor.[REMOVE]Fotnote: Teknisk Ukeblad , 1 October 2004: “Elektrisk Valhall-plattform”.

Ny Valhall prosess- og boligplattform
A powerful storm on the Valhall field in December 2011 tore loose grates and railings of the walkway. Photo: Unknown/BP/Norwegian Petroleum Museum

A massive wave which hit the field during a storm in November 2006 caused substantial damage to the process and quarters platforms. Several lifeboats were damaged, for example. This incident prompted the introduction of special emergency response measures when extreme weather was forecast, including the removal of personnel. That also prompted BP to speed up its VRD plans, and the project team came under heavy pressure to complete its work. The job was thereby schedule-driven from the start. Inadequate time and resources in the early phase meant the weight and dimensions of the new platform were underestimated. This was not spotted until late in the detail design stage.[REMOVE]Fotnote: Norwegian Petroleum Directorate report, October 2013, Evaluation of projects implemented on the Norwegian shelf , 33.

The combined installation became operational in January 2013. Subsidence had then gone so far that the cellar deck on all three existing platforms could be destroyed by a hundred-year wave.[REMOVE]Fotnote: Teknisk Ukeblad , 22 April 2005, “Valhall elektrifiseres”. They were therefore no longer safe for use in every kind of weather. The quarters platform is now shut during the winter and will be out of commission completely by the end of 2017.

Plans called for the VRD project to be completed in November 2010 at a cost of NOK 15.4 billion. However, it proved very demanding and extensive. More than two years late, it was brought in at a cost of NOK 24.9 billion. Well-related expenses also increased by NOK 10.8 billion, more than four times the original budget.[REMOVE]Fotnote: Norwegian Petroleum Directorate report, October 2013, Evaluation of projects implemented on the Norwegian shelf , 32.

The Valhall field is expected to be able to produce up towards 2050.

Published 25. June 2019   •   Updated 3. December 2020
© Norsk Oljemuseum
close Close

Technical Drawings and Documentation of the Valhall Platforms

person Filip Fremo Minge
Here you will find technical drawings and technical documentation of the platforms on the Valhall field.
— 00-07-00-PP-012-001 Elevation south
© Norsk Oljemuseum

Drilling Platform (DP)

Process and Compression Platform (PCP)

Quarters Platform (QP)

Riser Platform (RP)

Published 28. July 2015   •   Updated 26. January 2023
© Norsk Oljemuseum
close Close

Privacy Statement

person Norwegian Petroleum Museum
Some internet users are concerned about data confidentiality and the use of cookies downloaded to their computers from websites they visit. These small files are designed to store information about pages accessed, but cannot steal information from the visitor or their computer system.

The Norwegian Petroleum Museum utilises the Google Analytics tool, which installs cookies to collect and assess information about how visitors utilise its website.

These downloaded files can be used solely by www.kulturminne-valhall.no and the host computer’s owner. Google Analytics obtains only general web statistics – such as browser type, date and time, language, and the page the visitor came from.

Users can prevent cookies being stored on their computer by changing the preferences in their browser. These are usually found under such menu items as “preferences”, “internet options” or “internet alternatives”.

More information on cookies and how they are used can be found by clicking on help in the browser menu.

Published 9. August 2019   •   Updated 14. October 2020
© Norsk Oljemuseum
close Close